The progress under Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), at the end of the last month was as follows:
| Bharat Nirman target by March, 2012 | Revised coverage (provisional) under RGGVY | Achievement (as on 31.07.2011) |
Un/de-electrified village | 1,00,000 | 1,10,337 | 98,612 |
BPL | 175 lakh | 233.87 lakh | 168.86 lakh |
Giving this information in a written reply to a question in Lok Sabha today Minister of State for Power Shri K.C.Venugopal said the progress reports of rural electrification works under the scheme are sought from implementing agencies on a fortnightly basis as part of the Management Information System (MIS).